Dinah’s Hollow stabilisation scheme enters final months

Date:

A major engineering project to secure Dinah’s Hollow and reduce the risk of further landslips is on track to be completed by the end of the year.

Work on the C13 near Melbury Abbas began in January, with almost 1,500 soil nails – some nine metres long – now installed to stabilise the steep slopes. High-tensile wire mesh has also been fitted, while substantial drainage improvements are being carried out.

Video by Dorset Council

The hollow has suffered repeated landslips over many years, creating concerns over the long-term future of the route, which provides an important road link through north Dorset.

The remaining work includes completing drainage, installing new kerbs, resurfacing the road and landscaping. New bat and bird boxes will also be installed this autumn, alongside a specially selected mix of native seeds.

Dorset Council says more mature trees have been retained than originally anticipated, with new vegetation already appearing where trees have been removed. Ecologists have worked alongside engineers throughout the project, with construction planned around protected species including bats and hazel dormice.

Council leader Cllr Nick Ireland said: ‘Dinah’s Hollow has been a long-standing concern, so it’s great to see the project making such strong progress.

‘This is a complex engineering scheme, but the goal is simple: to provide a lasting solution that keeps people safe and communities connected, protects an important transport link and supports the local economy.’

North Dorset MP Simon Hoare recently visited the site with Cllr Ireland and local ward councillor Jane Somper.

He said: ‘I am really pleased that Dorset Council took on this project and is now bringing it through to fruition. I am staggered by how many mature trees they have been able to retain. It has been done sensitively and, for those who were concerned, growth is already coming through.

‘This is now a permanent fix to a long-term problem, which will be good news for residents and for businesses in north Dorset.’

The scheme remains scheduled for completion by the end of 2026.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

spot_img

Popular

More like this
Related

A Big Bad Night out for a very good cause

A charity cabaret that raised £5,200 two years ago...

A better picture of Black Friday TV deals

Black Friday offers can make November a good time...

A festive December at Wincanton Racecourse

December at Wincanton Racecourse is filled with festive fun,...

The turkeys that grew a little too well

In 1991, the Chillcotts took a chance on 100...